How to complete total estimated costs


On February 1, 2013, Arrow Construction Co. entered into a three year construction contract to build a bridge for a price of $8,000,000. During 2013, costs of $2,000,000 were incurred, with an estimated cost of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent and cash collected was $2,250,000. In 2014, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2014, billings were $2,750,000 and $2,475,000 cash was collected. The project was completed in 2015 after additional costs of $3,800,000 were incurred. The company's fiscal year end is December 31. Arrow uses the percentage of completion method. Calculate the amount of gross profit or loss to be recognized in each of the three years. This is how the problem should be set up this is the table I have to fill out. (below) 2013 2014 2015 Contract price Actual Cost to date Estimated costs to complete Total estimated costs Estimated gross profit (loss) (actual in 2015) Gross profit (loss) to be recognized

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: How to complete total estimated costs
Reference No:- TGS0685708

Expected delivery within 24 Hours