Flexible budget overhead for standard hours


Question 1. The Chesterfield Company uses standard costing. Overhead is applied at $12 per machine hour. Data for the month of March follows:

Actual overhead costs $ 97,000
Standard machine hours allowed for actual production 8,250
Actual machine hours used 8,700
Flexible budget overhead for standard hours allowed 104,400

The overhead volume variance is:

1. $2,000 favorable.

2. $7,400 favorable.

3. $5,400 unfavorable.

4. $7,400 unfavorable.

Question 2. The Downtown Company uses standard costing. Variable overhead is applied at $8 per direct labor hour. Data for the month of September follows:

Actual variable overhead costs $78,000
Standard hours allowed for actual production 10,000
Actual labor hours worked 9,800

The controllable overhead spending variance is:

1. $ 400 unfavorable.

2. $ 400 favorable.

3. $2,000 unfavorable.

4. $2,000 favorable.

Question 3. An automobile parts company has a standard labor rate of $12.50 per hour. In September the company produced 40,000 units using 100,000 labor hours. If the company experienced a favorable labor rate variance of $30,000 during the month, the actual labor rate per hour must be:

1. $12.80.

2. $12.20.

3. $11.75.

4. $12.50.

Question 4. A manufacturing company uses standard costing and applies overhead on the basis of direct labor hours. The company experienced the following results in August:

Standard direct labor hours allowed for actual production 9,000
Actual direct labor hours used 9,250
Predetermined overhead rate (per direct labor hour) $45
Flexible budget overhead for standard hours allowed $410,000

The overhead volume variance for the month is:

1. $5,000 unfavorable.

2. $5,000 favorable.

3. $11,250 unfavorable.

4. $6,250 favorable.

Question 5. A manufacturing company uses standard costing and applies overhead on the basis of direct labor hours. The company experienced the following results in December:

Predetermined overhead rate per labor hour $15.00
Standard direct labor hours allowed for actual production 14,000
Actual overhead costs $200,000

If the overhead volume variance was $6,000 unfavorable, the flexible budget overhead for standard hours allowed is:

1. $216,000.

2. $206,000.

3. $194,000.

4. $204,000.

Question 6. A manufacturing company uses standard costing and applies overhead on the basis of machine hours. The company experienced the following results in June:

Predetermined overhead rate per machine hour $7.50
Standard machine hours allowed for actual production 1,500
Actual machine hours used 1,800

If the controllable overhead spending variance was $3,500 favorable, actual overhead costs were:

1. $7,750.

2. $10,000.

3. $14,750.

4. $16,500.

7. A suit company has the following standards to make one suit:

Standard Quantity Standard Price
Direct materials 4 yards per unit $9.50 per yard
Direct labor 2 hours per unit $12.00 per hour

The company purchased 4,000 yards of material in March for $40,000. The company used 3,800 yards in March in order to make 900 suits. The direct materials price variance is:

1. $2.000 favorable.

2. $1,900 unfavorable.

3. $2,000 unfavorable.

4. $1,900 favorable.

Question 8. A suit company has the following standards to make one suit:

Standard Quantity Standard Price
Direct materials 4 yards per unit $9.50 per yard
Direct labor 2 hours per unit $12.00 per hour

The company used 13,000 yards of material in order to make 3,000 suits in April. The direct materials quantity variance is:

1. $9,500 favorable.

2. $9,500 unfavorable.

3. $12,000 favorable.

4. $12,000 unfavorable.

Question  9. The Gene Company's sales are 30% cash and 70% credit. 60% of credit sales are collected in the month of sale, 30% in the month following the sale, and 10% is collected two months after. Budgeted sales data is as follows:

June $200,000
July $100,000
August $150,000

Accounts receivable at the end of August are:

1. $21,000.

2. $70,000.

3. $147,000.

4. $49,000.

Question 10. An automobile parts company has a standard labor rate of $10.50 per hour. In September the company produced 10,000 units using 24,000 labor hours. If the company experienced a favorable labor rate variance of $18,000 during the month, the actual labor rate per hour must be:

1. $13.50.

2. $7.50.

3. $11.25.

4. $9.75.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Flexible budget overhead for standard hours
Reference No:- TGS01929369

Now Priced at $20 (50% Discount)

Recommended (97%)

Rated (4.9/5)