Find the probability of an expected completion time


Solve the below problem:

Q: A PERT Project has an expected completion time of 45 days with a variance of 9 days. Find the following probabilities:

A) P (T<= 48 days).

B) P (T>=41 days).

C) P (41<=T<=48 days).