Problem:

Your company's cost of capital is 12%. You are currently evaluating three projects that have the following cash flow streams:

 

Cash Flows at Time t

Project

0

1

2

3

4

A

-10,000

4,000

4,000

4,000

4,000

B

-10,000

0

0

0

50,000

C

-1,000

500

500

500

500

a) Find the payback period, discounted payback period, IRR, and NPV for each of the three projects.

b) Use the payback period to evaluate options A and B.  Which would you choose according to this method?  Why does payback period give the wrong answer?

c) Suppose projects A and C are mutually exclusive.  Use the IRR to establish which of the two you should undertake.  Why doesIRR give the wrong answer?

d) Determine whether Project A or C should be undertaken using incremental IRR.

Additional Information:

The question belongs to Finance and it is about evaluating three projects A, B and C with cash flows. The payback period, discounted payback period, IRR and NPV for each of the projects have been calculated.

Solution Preview :

Prepared by a verified Expert
Finance Basics: Find the payback period discounted payback periodnbspirr
Reference No:- TGS01108574

Now Priced at $40 (50% Discount)

Recommended (92%)

Rated (4.4/5)