Explain why the npv of a relatively long-term project


(10-1) What types of projects require the least detailed and the most detailed analysis in the capital budgeting process?

(10-2) Explain why the NPV of a relatively long-term project, defined as one for which a high percentage of its cash flows are expected in the distant future, is more sensitive to changes in the cost of capital than is the NPV of a short-term project.

(10-3) When two mutually exclusive projects are being compared, explain why the short-term project might be ranked higher under the NPV criterion if the cost of capital is high whereas the long-term project might be deemed better if the cost of capital is low. Would changes in the cost of capital ever cause a change in the IRR ranking of two such projects?

Why or why not?

(10-4) Suppose a firm is considering two mutually exclusive projects. One has a life of 6 years and the other a life of 10 years. Would the failure to employ some type of replacement chain analysis bias an NPV analysis against one of the projects? Explain.

(10-5)
Timing Differences

The Ewert Exploration Company is considering two mutually exclusive plans for extracting oil on property for which it has mineral rights. Both plans call for the expenditure of $10 million to drill development wells. Under Plan A, all the oil will be extracted in 1 year, producing a cash flow at t = 1 of $12 million; under Plan B, cash flows will be $1.75 million per year for 20 years.

a. What are the annual incremental cash flows that will be available to Ewert Exploration if it undertakes Plan B rather than Plan A? (Hint: Subtract Plan A's flows from B's.)

b. If the company accepts Plan A and then invests the extra cash generated at the end of Year 1, what rate of return (reinvestment rate) would cause the cash flows from reinvestment to equal the cash flows from Plan B?

c. Suppose a firm's cost of capital is 10%. Is it logical to assume that the firm would take on all available independent projects (of average risk) with returns greater than 10%?

Further, if all available projects with returns greater than 10% have been taken, would this mean that cash flows from past investments would have an opportunity cost of only 10%, because all the firm could do with these cash flows would be to replace money that has a cost of 10%? Finally, does this imply that the cost of capital is the correct rate to assume for the reinvestment of a project's cash flows?

d. Construct NPV profiles for Plans A and B, identify each project's IRR, and indicate the crossover rate.

Solution Preview :

Prepared by a verified Expert
Financial Accounting: Explain why the npv of a relatively long-term project
Reference No:- TGS02596248

Now Priced at $10 (50% Discount)

Recommended (96%)

Rated (4.8/5)