Explain the cost of the land and the new building


On March 1, 2013, Beldon Corporation purchased land as a factory site for 60,000. an old buildding on the property was demolished and construction began on a new building that was completed on December 15, 2013. Costs incurred during this period are listed below: Demolition of the old building 4,000 Architect's fees (for new building) 12,000 Legal fees for title investigation of land 2,000 Property taxes on land (for period beginning March 1, 2013) 3,000 Construction costs 500,000 Interest on construction loan 5,000 Salvaged materials resulting from the demolition of the old buidling were sold for 2,000. Question: Determine the amounts that Beldon should capitalize as the cost of the land and the new building.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Explain the cost of the land and the new building
Reference No:- TGS0716183

Expected delivery within 24 Hours