explain how you would estimate the project


Explain how you would estimate the project management activity.

Project management:

This effort is dependent onto two things as whether a full-time project manager is to be utilized or not and the in general expected period of the project. When a full-time manager is needed, in that case one simply multiplies the duration of the project with four to acquire the number of days' effort included (notice the main text for a discussion of why only four days a week is accessible for every person over the long run). When a half-time project manager is to be used, after that the number of weeks is multiplied with two and so on.

Request for Solution File

Ask an Expert for Answer!!
Project Management: explain how you would estimate the project
Reference No:- TGS0354128

Expected delivery within 24 Hours