Cost driver
If setup activity costs are $360,000, number of setups is 1,800, direct labor hours are 60,000, and machine hours are 36,000, then the setup activity cost driver rate, using the best cost driver for this situation, is :
(a) $200 per setup
(b) $6 per direct labor hour
(c) $10 per machine hour
(d) there is no appropriate cost driver rate