Drawing the project network


Problem:

Activity Immediate Predecessor (Time Weeks)
A - 1
B A 4
C A 3
D B 2
E C ,D 5
F D 2
G F    2
H E, G 3

1) Draw the project network.

2) How many weeks will it take to complete the project?

3) Which activities have slack, and how much?

4) What is the revised completion time for the project if duration of activity E is 3 weeks?

Solution Preview :

Prepared by a verified Expert
Project Management: Drawing the project network
Reference No:- TGS01768525

Now Priced at $20 (50% Discount)

Recommended (93%)

Rated (4.5/5)