Discuss how some of the afore-mentioned elements affected


The impact of a change can affect:

-Just the direct activity itself

-All downstream activities, and

-The project's fixed cost, or project overhead, based on an increase/decrease in overall project duration

Remember that depending on what the change is, you may have to go through all, or a large portion of the planning processes all over again, including, but not limited to:

Scope

Risk

Schedule

Cost

Find a project online (make sure to cite the source) and evaluate the impact of the change in regards to the criteria above (at a minimum). Discuss how some of the afore-mentioned elements affected the project, and what steps were taken in change control to mitigate them.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Discuss how some of the afore-mentioned elements affected
Reference No:- TGS02902997

Expected delivery within 24 Hours