Developing and using a predetermined overhead rate


Question:

Developing and Using a Predetermined Overhead Rate

Assume that the following predictions were made for 2009 for one of the plants of Milliken & Company:

Total manufacturing overhead for the year

$44,000,000

Total machine hours for the year

2,000,000

Actual results for February 2009 were as follows:

Manufacturing overhead

$5,480,000

Machine hours

310,000

(a) Determine the 2009 predetermined overhead rate per machine hour.

(b) Using the predetermined overhead rate per machine hour, determine the manufacturing overhead applied to Work-in-Process during February.

(c) As of February 1, actual overhead was under applied by $500,000. Determine the cumulative amount of any over applied or under applied overhead at the end of February.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Developing and using a predetermined overhead rate
Reference No:- TGS02053353

Expected delivery within 24 Hours