Develop an in-depth schedule for the project you selected


Assignment

Part 1

Develop an in-depth schedule for the project you selected and used to develop the statement of work and work breakdown structure in Unit III. Please refer to the Integrated Project in Chapter 10 on page 363 (Project Scheduling) of the textbook for more information. Be sure to include the following components:

• an activity precedence diagram,
• an activity duration table, and
• a network diagram and Gantt charts.

Part 2

Complete Case Study 10.1: Project Scheduling at Blanque Check Construction on page 360 of the textbook, and answer the three questions at the end.

Part 3

Develop a network activity chart, and identify the critical path for a project based on the information provided in the Gantt chart below. Draw the activity network as a Gantt chart. What is the expected duration of the project?

Activity

Expected Duration

Predecessor

A

5 days

----

B

10 days

A

C

8 days

A

D

1 day

A

E

5 days

B, C

F

10 days

D, E

G

14 days

F

H

3 days

G

I

12 days

F

j

6 days

H, I

Part 4

Using the information provided in the Gantt chart below, construct the project activity network using the activity-on-node (AON) methodology, and label each node. Identify the critical path and other paths through the network.

Activity

 

 

Duration

 

Predecessors

A

 

 

3

 

--

B

 

 

5

 

A

C

 

 

7

 

A

D

 

 

3

 

B, C

E

 

 

5

 

B

F

 

 

4

 

D

G

 

 

2

 

C

H

 

 

5

 

E, F, G

Activity

Duration

ES

EF

LS

 

LF

Slack

A

3

0

3

0

 

0

--

B

5

3

8

8

 

13

5

C

7

3

10

3

 

10

--

D

3

10

13

13

 

13

--

E

5

8

12

13

 

17

5

F

4

13

17

13

 

17

 

G

2

10

12

15

 

17

5

H

5

17

22

17

 

22

--

Format your assignment according to the following formatting requirements:

1. The answer should be typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides.

2. The response also include a cover page containing the title of the assignment, the student's name, the course title, and the date. The cover page is not included in the required page length.

3. Also Include a reference page. The Citations and references should follow APA format. The reference page is not included in the required page length.

Attachment:- Project-Template.rar

Solution Preview :

Prepared by a verified Expert