Determining the project expected npv of desai industries


Problem:

Desai Industries is analyzing an average-risk project, and the following data have been developed.  Unit sales will be constant, but the sales price should increase with inflation.  Fixed costs will also be constant, but variable costs should rise with inflation.  The project should last for 3 years, it will be depreciated on a straight-line basis, and there will be no salvage value. No change in net operating working capital would be required.  This is just one of many projects for the firm, so any losses on this project can be used to offset gains on other firm projects.  

Required:

Question: What is the project's expected NPV?

WACC 10.0%
Net investment cost (depreciable basis) $200,000
Units sold 39,000
Average price per unit, Year 1 $25.00
Fixed op. cost excl. depr. (constant) $150,000
Variable op. cost/unit, Year 1 $20.20
Annual depreciation rate 33.333%
Expected inflation rate per year 5.00%
Tax rate 40.0%


A) 
B) 
C) 
D) 
E) 

Note: Show supporting computations in good form.