Determining project risk adjusted net present value


Problem:

The Oak Grove Corporation is considering two mutually exclusive projects. Both require an initial outlay of $10,000 and will operate for 5 years. Project A will produce expected cash flows of $5,000 per year for years 1 through 5, whereas Project B will produce expected cash flows of $6,000 per year for years 1 through 5. Because project B is the riskier of the two projects, the management of Oak Grove Corporation has decided to apply a required rate of return of 15 percent to its evaluation but only a 12 percent required rate of return to project A. Determine each project's risk adjusted net present value.

Show calculations and select the correct answer from these multiple choice options:

A. Project A $9,154 and Project B $12,367.

B. Project A $8,950 and Project B $11,876.

C. Project A $8,025 and Project B $10,112.

D. Project A $7,659 and Project B $13,267.

Solution Preview :

Prepared by a verified Expert
Finance Basics: Determining project risk adjusted net present value
Reference No:- TGS02049341

Now Priced at $20 (50% Discount)

Recommended (99%)

Rated (4.3/5)