Determine the precedence relationships and activity times


Assignment:

A plant is planning to install a new shift to its existing production capacity. There are a number of activities from legal requirements to human resource issues to be completed before the shift becomes productive. The management has determined the activities required to complete the project, the precedence relationships, and activity times as follows:

790_P 15.jpg

Answer following questions:

a. Draw project network for the above project, compute the early, late, and slack activity times; must use the given legend of the node. Must include start and finish node.

b. What is the project completion time in days?

c. State critical path/s for the above project?

d. Which activity/ies is/are merge activity/ies?

e. Which activity/ies is/are burst activity/ies?

f. Among non critical activities, which activity has the most slack time?

g. Draw the giant chart of the project.

h. If there is delay in completion of activity 'M' by 6 days, what will be the impact on project completion time? Why?

i. If there is delay in completion of activity 'F' by 3 days, what will be the impact on project completion time? Why?