Determine the npv for both projects


Problem: Letterman Hospital expects Project A and B to generate the following cash flows:

Givens (in thousands) years 0 1 2 3 4 5
1 Initial investment      0($2,500)
2 Net operating cash flows for project A 1$1,800 2$1,600 3$900 4$400 5$200
3 Net operating cash flows for project B 1$200 2$400 3$900 4$1,600 5$1,800
4 Discount rate for Part a 15%
5 Discount rate for Part b 5%

a. Determine the NPV for both projects using a cost of capital of 15 percent

b. Determine the NPV for both projects using a cost of capital of 5 percent.

c. At a 5 percent cost of capital, which project should be accepted? At a 15 percent cost of capital, which project should be accepted? Explain

Goodbar Practice expects projects 1 and 2 to generate the following cash flows:

Project 1 (in thousands) years   0 1 2 3 4 5
Givens   0 ( $2,000)
Net operating cash flows         1$200 2 $300 3 $500 4$1,000 5$1,790

Project 2 (in thousands)
Givens 0($3,800)
Net operating cash flows  1$1,000 2$1,000 3$1,000 4$1,000 5$1,000

a. Determine the payback for the both projects.

b. Determine the IRR.

c. Determine the NPV at a cost of capital of 12 percent.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Determine the npv for both projects
Reference No:- TGS01891759

Now Priced at $25 (50% Discount)

Recommended (97%)

Rated (4.9/5)