Determine the earliest-latest and slack times for activity


Activity Immediate Predecessor Time (days)
A - 3
B - 7
C A 4
D B 2
E- C,D 5
F - A 6
G - E,F 3

The activity times for the project given above. Determine the earliest, latest, and slack times for each activity. Then Determine the critical path.