Compute the total overhead variance compute the overhead


Assignment

1. A job cost sheet of Fugate Company is given below.

 

Job Cost Sheet

JOB NO.  172

Quantity 1,500

FOR James Company

Date Completed   5/31

Date

Direct Materials

Direct Labor

Manufacturing overhead

5/10

1,330

 

 

12
15
22
24

1,120


1,000


550
480


825
720

27
..      31

1,870


670

1,005

Cost of completed job:
Direct materials
Direct labor


___________
__________

Manufacturing Overhead             ________
Total cost                                 ________
Unit cost                                   ________

Cost of completed job: Direct materials Direct labor :..

Manufacturing Overhead Totalcost
Unit cost

REQUIREMENTS:

(a) Answer the following questions.

(1) What is the predetermined manufacturing overhead rate?
(2) What are the total cost and the unit cost of the completed job? (b) Prepare the entry to record the completion of the job.
(Problem is worth 50 points)

2. TheNitrogen Fixation Department of Tomco Company began the month of December with beginning work in process of 4,000 units that are 100% complete as to materials and 30% complete as to conversion costs. Units transferred out are 12,000 units. Ending work in process contains 10,000 units that are 100% complete as to materials and 40% complete as to conversion costs.

REQUIREMENTS:

Compute the equivalent units of production for materials and conversion costs for the month of December.

3. Compute activity-based costing rates from the following budgeted datafor Upton Golf Co.:

Activity Cost Pool

Budgeted Cost

Budgeted Cost Driver

Designing

$2,550,000

75,000 designer hours

Machining

525,000

21,000 machine hours

Packing

620,000

31,000 labor hours

4. Caroline, Inc. planned to produce 20,000 units of product and work 100,000 direct labor hours In 2016. Manufacturing overhead at the 100,000 direct labor hours level of activity was estimated to be:

Variable manufacturing overhead

$ 700,000

Fixed manufacturing overhead

300.000

Total manufacturing overhead

$1,000,000

At the end of 2016, 19,000 units of product were actually produced and 98,000 actual direct labor hours were worked. Total actual overhead costs for 2016 were $935,000.

REQUIREMENTS:

(a) Compute the total overhead variance.
(b) Compute the overhead controllable variance.
(c) Compute the overhead volume variance.

Solution Preview :

Prepared by a verified Expert
Financial Accounting: Compute the total overhead variance compute the overhead
Reference No:- TGS02246743

Now Priced at $25 (50% Discount)

Recommended (91%)

Rated (4.3/5)