Compute the total overhead variance


Question: Bluecap Co. uses a standard cost system and flexible budgets for control purposes. The following budgeted information pertains to 2016:

Denominator volume-number of units 8,000

Denominator volume-percent of capacity 80%

Denominator volume-standard direct labor hours 24,000

Budgeted variable factory overhead cost at denominator volume $103,200

Total standard factory overhead rate per direct labor hour $15.10

During 2016, Bluecap worked 28,000 direct labor hours and manufactured 9,600 units. The actual factory overhead cost for the year was $14,000 greater than the flexible budget amount for the units produced, of which $6,000 was due to fixed factory overhead. In preparing a budget for 2017 Bluecap decided to raise the level of operation to 90% of capacity (a level it considers to be "practical capacity"), to manufacture 9,000 units at a budgeted total of 27,000 direct labor hours.

Required: Compute the total overhead variance in 2016 for Bluecap Co.?

a. $15,040 favorable

b. $14,000 unfavorable

c. $37,840 favorable

d. $37,840 unfavorable

e. $17,280 favorable

Our Total Overhead Variance Assignment Help service not just restrict to offer you the topmost assignment solution, however, always provide the step by step well-researched assignment solution, so that, you will gain comprehensive knowledge too.

Tags: Total Overhead Variance Assignment Help, Total Overhead Variance Homework Help, Total Overhead Variance Coursework, Total Overhead Variance Solved Assignments

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Compute the total overhead variance
Reference No:- TGS03047570

Expected delivery within 24 Hours