Compute the projects net present value- should the project


A firm wishes to bid on a contract that is expected to yield the following after-tax net cash flows at the end of each year:

Year

Net Cash Flow

1

$ 5,000

2

8,000

3

9,000

4

8,000

5

8,000

6

5,000

7

3,000

8

$-1,500

To secure the contract, the firm must spend $ 30,000 to retool its plant. This retooling will have no salvage value at the end of the eight years. Comparable investment alternatives are available to the firm that earn 12 percent compounded annually. The depreciation tax benefit from the retooling is reflected in the net cash flows in the table.

a. Compute the project's net present value.

b. Should the project be adopted?

c. What is the meaning of the computed net present value figure?

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Compute the projects net present value- should the project
Reference No:- TGS02138003

Expected delivery within 24 Hours