Compute the mean and variance of the npw for project one


Problem

A company is considering two investment projects whose present values are described as follows:

Project 1: NPW(10%) = 20 X + 8 XY,

where X and Y are statistically independent discrete random variables with the following distributions:

Variable X

Variable Y

Event

Probability

Event

Probability

$20

0.55

$11

0.3

$40

0.45

$22

0.7

Project 2:

NPW (10%)

Probability

$0

0.23

$300

0.20

$1500

0.37

$2200

0.2

[a] Compute the mean and variance of the NPW for project 1 (NPW1),

[b] Identify the joint outcome(s) by the pair of NPW values (NPW1 = ? and NPW2=?) such that Project 2 is considered better than Project 1. Note there are a total of 4 possible NPW1 values and four given NPW2 values. Therefore, you have a total of 16 different pairs of NPW values.

[c] Calculate the probability that Project 1 is better than Project 2?

The response should include a reference list. Double-space, using Times New Roman 12 pnt font, one-inch margins, and APA style of writing and citations.

Request for Solution File

Ask an Expert for Answer!!
Microeconomics: Compute the mean and variance of the npw for project one
Reference No:- TGS02945855

Expected delivery within 24 Hours