Compute the direct material quantity variance for august


A company established a direct material standard of 2 pounds of material at a cost of $6 per pound for unit produced. During August the company produced 6,000 units of product. 10,000 pounds of direct material which cost $6.50 per pound were used in the production process. Compute the direct material quantity variance for August.