Compute arrow direct material variances


Assignment Problem: Straightforward Variance Analysis

Arrow Enterprises uses a standard costing system. The standard cost sheet for product No. 549 follows:

Direct materials: 4 units @ $6.50 $26.00

Direct labor: 8 hours @ $8.50 68.00

Variable factory overhead: 8 hours @ $7.00 56.00

Fixed factory overhead: 8 hours @ $2.50 20.00

Total standard cost per unit $170.00

The following information pertains to activity for December:

1) Direct materials acquired during the month amounted to 26,350 units at $6.40 per unit. All materials were consumed in operations.

2) Arrow incurred an average wage rate of $8.75 for 51,400 hours of activity.

3) Total overhead incurred amounted to $508,400. Budgeted fixed overhead totals $1.8 million and is spread evenly throughout the year.

4) Actual production amounted to 6,700 completed units.

Assignment Instructions:

a. Compute Arrow's direct material variances.

b. Compute Arrow's direct labor variances.

c. Compute Arrow's variances for factory overhead.

Are you still exhausted because of your assignment dilemmas? Don't worry! Just approach our Straightforward Variance Analysis Assignment Help service and you will witness the remarkable difference in your academic grades.

Tags: Straightforward Variance Analysis Assignment Help, Straightforward Variance Analysis Homework Help, Straightforward Variance Analysis Coursework, Straightforward Variance Analysis Solved Assignments, Direct Material Variances Assignment Help, Direct Material Variances Homework Help, Labor Variances Assignment Help, Labor Variances Homework Help, Factory Overhead Assignment Help, Factory Overhead Homework Help

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Compute arrow direct material variances
Reference No:- TGS03041822

Expected delivery within 24 Hours