Completion revenue recognition process


You are the Senior Accountant for the Patty Corporation which has several divisions. They each keep their own accounting books and have chosen the appropriate method of revenue recognition based on their operations.

The Pickle construction division was working on one project for the 2012 fiscal year. They use the percentage of completion revenue recognition method.

Contract for new administration building
Total Contract Amount $ 60,000,000
Contract Grant Date August 14, 2012
Construction Began September 1, 2012

Estimated Cost to Complete at beginning of contract $ 52,000,000
Estimated Time to Complete Project 2 years

As of Dec 31, 2012
Construction Costs incurred to date $ 14,140,000
Billings to date $ 19,500,000
Expected costs to complete $ 36,360,000

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Completion revenue recognition process
Reference No:- TGS054012

Expected delivery within 24 Hours