Completed-contract accounting


Problem: On February 1, 2007, Nance Contractors agreed to construct a building at a contract price of $6,000,000. Nance estimated total construction costs would be $4,000,000 and the project would be finished in 2009. Information relating to the costs and billings for this contract is as follows:

Total costs incurred to date     $1,500,000     $2,640,000     $4,600,000
Estimated costs to complete      2,500,000       1,760,000          -0-
Customer billings to date          2,200,000       4,000,000     5,600,000
Collections to date                   2,000,000        3,500,000    5,500,000

Instructions:

Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and for completed-contract accounting, show the gross profit that should be recorded for 2007, 2008, and 2009.

Percentage-of-Completion Completed-Contract Gross Profit Gross Profit

2007 ____________ 2007 ____________
2008 ____________ 2008 ____________
2009 ____________ 2009 ____________

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Completed-contract accounting
Reference No:- TGS01738212

Now Priced at $20 (50% Discount)

Recommended (90%)

Rated (4.3/5)