Complete the new performance report for the quarter


Several years ago, Shipley Corporation developed a comprehensive budgeting system for profit planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system.

A typical departmental cost report for a recent period follows:

Assembly Department
Cost Report
For the Month Ended March 31

Planning
Budget
Actual
Results
Variances
Machine-hours
20,000
15,000


Variable costs:






Supplies $ 11,700 $ 11,100 $ 600 F
Scrap
43,500
40,600
2,900 F
Indirect materials
138,000
115,400
22,600 F
Fixed costs:






Wages and salaries
79,000
84,700
5,700 U
Equipment depreciation
109,000
109,000
-








Total cost $ 381,200 $ 360,800 $ 20,400

F

Complete the new performance report for the quarter, based on Flexible Budget Performance approach.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Complete the new performance report for the quarter
Reference No:- TGS0682089

Expected delivery within 24 Hours