Case studies in finance fin3csf - the development of a


CASE STUDY: FINANCIAL MODELLING AND ETHICAL ISSUES IN FINANCE

Engie Group, a French-owned global energy company (formerly known as GDF Suez) which is the current owner and operator of the Loy Yang B power station precinct and operation located in the La Trobe Valley in South-Eastern Victoria, is assessing the feasibility of the development and operation of a new coal-fired power station in the La Trobe Valley region. The basis for this new project proposal is derived from a number of perspectives: i) the impending de-commissioning of the Loy Yang B power station at the end of its indicative 30- year operating life in 2025; ii) the availability of coal resources in the La Trobe Valley region to support ongoing coal-fired electricity generation activity; iii) the experience that the company has in the Victorian electricity market and expectation of ongoing population growth and demand for electricity provision; iv) uncertainty regarding the expected availability and sufficiency of alternative electricity generation sources at the proposed time of de- commissioning of the current Loy Yang B power station and v) perceived ongoing profitability from coal-fired electricity generation activity.

The company has completed some preliminary project development and planning work. The proposal involves the construction of the new power station in two stages, based on the following envisaged construction and operational schedule:

Table 1: Project Construction and Operation Summary

Year

Project Activity

2019

Construction begins on the project (assumed to be continuous until 2025)

2024

Commissioning of Generation Unit A

2026

Commissioning of Generation Unit B

2058

Generation Unit A ceases operation (based on a 35-year expected useful life)

2060

Generation Unit B ceased operation (based on a 35-year expected useful life)

As part of this planning the company has forecast the following specifications, requirements and parameters for the new project:

- The company would need to acquire access to land adjacent to the current coal open-cut facility it is operating to supply the Loy Yang B power station, which is owned by the State Government. The project would also need the overall approval of the State and Federal Governments to develop the project, as it would have a significant impact on electricity supply to the national electricity grid and also have major consequences for the future emission targets and objectives both locally and the overall commitment of the Australian Government to lower environmental emissions 26-28% relative to 2005 emission levels by 2030.

- Generating Units A and B would both be 250 Megawatt (MW) generating units representing self-generating energy processors functioning on coal as the primary input and incorporating a steam-to-turbine production method as the method of electricity generation. A 250MW generating unit operating at full capacity will produce 250 MW hours of electricity per hour.

- The useful life of each generating unit is 35 years.

- The average operating capacity factor of the power station is expected to be 90%.

- Expected within-station usage of 5% of the total electricity generated.

- The power station generation units are assumed to operate 24 hours a day, 365 days a year (ignoring leap years and industrial disputes).

- Due to the on-demand (base-load) nature of the electricity-generation process and the unavailability of a cost-effective storage source, 10% of the available electricity generated, on average, is not expected to be transmitted to the distribution grid or sold.

- The average tariff at which electricity can be sold to contractual customers (such as electricity retailers) or the national electricity regulator is $190.00 per Megawatt hour (in real terms). This tariff takes into account the cost and delivery of coal for operation of the power station, the replacement value of power station assets and an emission charge component.

- Operating and maintenance costs (outlined in Table 3 below) incorporate depreciation allowances on the capital construction costs, Government land charges and duties, staffing costs, inventory and supplies, and utilities costs (excluding electricity which is accessed directly from the operation of the power station).

- The company expects to have to pay company tax on profits created by operation of the power station at an average future marginal tax rate of 25%.

- The average rate of inflation over the life of the project is assumed to be 2.20% per annum.

- The estimated after-tax cost of capital (WACC) for the power station project based on the envisaged cash flow risk and target financing structure is 8.50% per annum.

- All figures are expressed in June 30, 2016 real dollars.

- All information is as at June 30, 2016.

- Note that 1 Megawatt hour represents 1,000 Kilowatt hours.

Estimated construction costs for the new power station project are as follows:

Table 2: Forecast Project Capital Construction Costs

Year

Estimated project construction costs

2019

$160.5 million

2020

$167.5 million

2021

$160.0 million

2022

$167.0 million

2023

$152.5 million

2024

$110.0 million

2025

$85.0 million

Estimated operating and maintenance costs for the new power station project are as follows:

Table 3: Forecast Annual Operating and Maintenance Costs

Year

Estimated Operating and Maintenance costs

2024

$70.0 million

2025

$95.0 million

2026

$118.5 million

2027 - 2058

$105.0 million

2059

$80.0 million

2060

$65.0 million

Engie Group has hired your consulting firm to conduct the financial modelling and capital budgeting assessment of the potential power station project, as well as to act as its adviser in dealing with the State and Federal Governments in negotiating the project approval process.

Required:

This case study requires the completion of the following tasks:

- The development of a spreadsheet model representing the cash flows associated with the power station project, and the assessment of the project using a range of capital budgeting evaluating techniques

- The completion of a risk assessment based on conducting sensitivity analysis of the project valuation focusing on key parameters impacting on the project's operation, feasibility and cash flows.

- Based on the project modelling and sensitivity analysis, a recommendation as to the feasibility of the project.

- The preparation of a proposal for the respective Governments providing justification for why approval for the project should be provided.

Attachment:- spreadsheet model.xlsx

Attachment:- notes.pdf

Solution Preview :

Prepared by a verified Expert
Financial Management: Case studies in finance fin3csf - the development of a
Reference No:- TGS01575432

Now Priced at $60 (50% Discount)

Recommended (90%)

Rated (4.3/5)