capital expenditure programstanaway had assumed


Capital Expenditure Program

Stanaway had assumed responsibility for the Glenlines Plant only twelve months previously and undertook a detailed review of the operations and discovered significant opportunities for improvement in polypropylene production. Some of these opportunities stemmed from the deferral of maintenance over the preceding five years. In an effort to enhance the operating results of the Plant, the previous manager had limited capital expenditures to only the most essential. Now, what had been routine and deferrable was becoming essential. Other opportunities stemmed from changing the current plant design that would save energy and/orimprove the process flow:

(1) relocating and modernising rail tanks unloading areas. 

(2) refurbishing the polymerisation tank to achieve greater throughput; and

 (3) renovating the compounding plant to increase extrusion throughput.

Stanawayanticipatedexpenditure of $7 million on this program. The entire polymerisation line would need to be shut down for 60 days, however, and because the Sydney plant was operating near capacity, Glenlines' customers would buy from competitors. Hawkins believed the lost customers would not be permanent. The benefits would be a lower energy requirement as well as a 7 percentgreater manufacturing throughput. In addition, the project was expected to improve gross margin (before depreciation and energy savings) from 11.5 percent to 12.9 percent.

Glenlines currently produced 135,000 metric tons of polypropylene pellets per year. Currently, the price of polypropylene averaged $611 per ton for Biotechnique's product mix. The tax rate required in capital-expenditure analyses was 35 percent. Dawkins discovered that any existing plant facilities to be replaced had been fully depreciated. New assets would be depreciated on a straight line basis over 15 years, the expected life of the assets. The increased throughput would necessitate a one-time increase of  inventory equal in value to 3.0 percent of cost of goods. Dawkins included in the first year of his forecast "preliminary engineering costs" of $500,000, which had been spent over the preceding 9 months on efficiency and design studies of the renovation. Finally, the corporate manual stipulated that overhead costs be reflected in project analyses at the rate of 3.5 percent per yearof the cost of assets acquired in the project.

Request for Solution File

Ask an Expert for Answer!!
Business Management: capital expenditure programstanaway had assumed
Reference No:- TGS0204803

Expected delivery within 24 Hours