You are the project manager of the Carpet Installation Project for a new building. Your BAC is $600,000. You are now 40% complete with the project though your plan called for you to be 45% complete with the work by this time. What is your earned value?
1.	$240,000
2.	$270,000
3.	$30,000
4.	$30,000