Calculate the total value of the finished goods inventory


Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job A260. At the end of October, the job cost sheets for these jobs contained the following data:


Job A256 Job A257 Job A258 Job A260
  Beginning balance $ 1,200 $ 500 $ 0 $ 0
  Charged to the jobs during October:







     Direct materials $ 2,600 $ 3,500 $ 1,400 $ 3,500
     Direct labor $ 800 $ 1,000 $ 600 $ 400
     Manufacturing overhead applied $ 1,200 $ 1,500 $ 900 $ 600
  Units completed
100
0
200
0
  Units in process at the end of October
0
400
0
500
  Units sold during October
80
0
40
0

Jobs A256 and A258 were completed during October. The other two jobs had not yet been completed at the end of October. There was no finished goods inventory on October 1.

 In October, overhead was overapplied by $800. The company adjusts its cost of goods sold every month for the amount of the underapplied or overapplied overhead.

Required:
1.

Using the direct method, what is the cost of goods sold for October? (Round your intermediate calculations to 2 decimal places.)

2.

What is the total value of the finished goods inventory at the end of October? (Round your intermediate calculations to 2 decimal places.)


3.

What is the total value of the work in process inventory at the end of October?

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Calculate the total value of the finished goods inventory
Reference No:- TGS0684405

Expected delivery within 24 Hours