Calculate the schedule variance for each task and the total


1. The project is linear, which means that the progress and spending occurs at a constant rate. Our crack project team of highly skilled associates has worked diligently and put in extra hours to keep the project going.  Our accounting department has provided the following data at the end of month 4:

Actual cost to date = $88,800

Planned expenditures to date = $101,000

The CFO is excited and has sent you an email congratulating you for being 12.07% under budget. However, is it really time to hold a team celebration? That would be fun but your project manager mentality kicks in. Those numbers look good but how are we 'really' doing? To understand the true project performance, we need to apply earned value techniques.

The missing piece we need is Earned Value (i.e. what we have actually accomplished so far). You meet with your team and find that only 6 of the 7 tasks scheduled to be complete by the end of month 4 have actually been completed. Task 7 isn't even started!This information gives you the final data you need to apply 'Earned Value'and develop an objective analysis.

1. What are the PV, EV, and AC for the project at the end of month 4?

2. What are the SV, CV, SPI, and CPI for the project?

3. Assess the project performance to date? Do you get to have the celebration?

 

2. Project Network Diagram

 

669_Project Network Diagram.png

Critical Path (CP) = B - E - G = 14 days                                                                                       

1. Calculate the schedule variance for each task and the total project.

2. Calculate the cost variance for each task and the total project.

3. What is your assessment of the project at this time?

Solution Preview :

Prepared by a verified Expert
Managerial Accounting: Calculate the schedule variance for each task and the total
Reference No:- TGS0775215

Now Priced at $30 (50% Discount)

Recommended (93%)

Rated (4.5/5)