Calculate the npv for each project over its life rank the


Seattle Manufacturing is considering the purchase of one of three mutually exclusive projects for improving its assembly line.

The firm plans to use a 14 percent cost of capital to evaluate these equal-risk projects. The initial outlay and the annual cash outflows over the life of each project are shown in the following table

Initial Outlay (CF0)

Project X

$ 156,000

Project Y

$ 104,000

Project Z

$ 132,000

Year (t)

 

Cash Outflows (CFt)

 

1

$ 34,000

$ 56,000

$ 30,000

2

50,000

56,000

30,000

3

66,000

-

30,000

4

82,000

-

30,000

5

-

-

30,000

6

-

-

30,000

7

-

-

30,000

a. Calculate the NPV for each project over its life. Rank the projects in descending order based on NPV.

b. Use the equivalent annual cost (EAC) method to evaluate and rank the projects in descending order based on the EAC.

c. Compare and contrast your findings in parts (a) and (b). Which project would you recommend that the firm purchase? Why?

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Calculate the npv for each project over its life rank the
Reference No:- TGS01731120

Expected delivery within 24 Hours