Calculate the irr the npv and the mirr for each project and


Edelman Engineering is considering including two pieces of equipment, a truck and an overhead pulley system, in this year's capital budget. The projects are independent. The cash outlay for the truck is $17,100 and that for the pulley system is $22,430. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows:

Year truck pulley
1 $5100 $7500
2 5100 7500
3 5100 7500
4 5100 7500
5 5100 7500
Calculate the IRR, the NPV, and the MIRR for each project, and indicate the correct accept-reject decision for each.

 

Request for Solution File

Ask an Expert for Answer!!
Finance Basics: Calculate the irr the npv and the mirr for each project and
Reference No:- TGS0631464

Expected delivery within 24 Hours