Bc bridgesinc wascontracted to build an overpass what gross


Assignment

B.C. Bridges Inc. was contracted to build an overpass for the Horseshoe Bay Ferry Terminal. The contracthad a fixed price of $1,200,000. The over pass would take four years to build. B.C. Bridges Inc. received a depositof $150,000 onsigning the contract in 20X10. During the course of construction, B. C. Bridges Inc. experienced and estimated costs as follows:

December 31, 20X10 Total costs incurred to date

December 31, 20X10

Total costs incurred to date
Estimated additional costs to complete construction

$175,000
$600,000

December 31, 20X11

Total costs incurred to date
Estimated additional costs to complete construction

$450,000
$500,000

December 31, 20X12

Total costs incurred to date
Estimated additional costs to complete construction

$800,000
$450,000

December 31, 20X13

Total costs incurred to date
Estimated additional costs to complete construction

$1,100,000
$0 as contract is

Required:

a. Calculate the gross profit B. C. Bridges Inc. should recognize under the % of completion method for each year of the contract.

b. What gross profit would be recognized in 20X12 and 20X13 under the completed contract method?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Bc bridgesinc wascontracted to build an overpass what gross
Reference No:- TGS02590058

Now Priced at $25 (50% Discount)

Recommended (96%)

Rated (4.8/5)