An all-equity firm is considering the following


An all-equity firm is considering the following projects:

Project    Beta    IRR

W           0.8      9.40%

X            0.95    10.9

Y           1.15    13.0

Z            1.45    14.2

The T-bill rate is 3.5%, and the expected return on the market is 11%.

a. Which projects have a higher expected return than the firm's 11% cost of capital?

b. Which projects should be accepted?

c. Which projects would be incorrectly accepted or rejected if the firm's overall cost of capital was used a hurdle rate?

As per the textbook solution, projects Y and Z are the answer to first question. But how do we know that? Also for solution to part C, project X is said to be incorrectly rejected and project Z incorrectly accepted. How so? Please help me understand.

Request for Solution File

Ask an Expert for Answer!!
Financial Management: An all-equity firm is considering the following
Reference No:- TGS01359124

Expected delivery within 24 Hours