A state government is considering construction of a flood


A state government is considering construction of a flood control dike having a life span of 12 years. History indicates that a flood occurs every 4 years, on average, and causes $500,000 in damages on each occasion. If the state uses a MARR of 12% per year and expects every public works project to have a benefit-cost ratio of at least 1.0, what is the maximum investment (to the nearest whole dollar) that will be allowed for the dike?

Request for Solution File

Ask an Expert for Answer!!
Business Economics: A state government is considering construction of a flood
Reference No:- TGS01112980

Expected delivery within 24 Hours