a riskadverse manager is considering two projects


A risk=adverse manager is considering two projects. the first project involves expanding the market for hotdog; the second involves expanding the market for Champaign drink. There is a 10 percent chance for a recession and a 90 percent chance for a economic boom. During a boom, the hotdog project will lose $10,000.00 whereas the Champaign drink project will earn $20,000.00. During a recession, the hotdog project will earn $12,000.00 and the Champaign project will lose $8,000.00. If the alternative is earning $3,000.00 on government Treasury bill (T-bill), what should the manager do? Why?