A producer of refrigerator compressors wants to implement a


1. A producer of refrigerator compressors wants to implement a just-in-time production line to support demand from a neighboring appliance manufacturer. Demand from the appliance manufacturer is for 200 compressors a day. The production lead time is 2 days and the producer wants to have a 10% safety stock factor. This producer has also cut setup costs such that the optimal production quantity is 50 units.

a. How many kanbans does this producer of compressors require? (Display your answer to the most appropriate whole number.)

2. Durabright wants to establish kanbans to feed a newly installed work cell for its line of LED traffic signal lamps. The daily production (demand) rate for this new family of products is 60 units. The supplier lead time for the bulb housing, used by all products in this product family, is 4 days. They want to keep 1.25 days of safety stock of this housing on hand (the safety stock factor).

a. The kanban size for the bulb housing components is 20 units. How many kanbans do they require? (Display your answer to the most appropriate whole number.)

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A producer of refrigerator compressors wants to implement a
Reference No:- TGS02569892

Expected delivery within 24 Hours