a contractor submits a bid on a project for which


A contractor submits a bid on a project, for which more research and development work needs to be done. It is estimated that the total cost of satisfying the project specifications will be $20 million, plus the cost of the further research and development work. The contractor views the cost of this work as a random variable with mean $4 million and standard deviation $1 million. The contractor wishes to submit a bid such that his expected profit will be 10% of his expected costs.

a) What should be the bid?

b) If this bid is accepted, what will be the standard deviation of the profit made on the project?

Request for Solution File

Ask an Expert for Answer!!
Macroeconomics: a contractor submits a bid on a project for which
Reference No:- TGS0500077

Expected delivery within 24 Hours