A calculate planning and operating variances following the


The following variances have been calculated in respect of a new product:

Direct labour efficiency variance $14,700 Favourable

Direct labour rate variance $ 5,250 Adverse

The variances were calculated using standard cost data which showed that each unit of the product was expected to take 8 hours to produce at a cost of $15 per hour. Actual output of the product was 560 units and actual time worked in the manufacture of the product totalled 3,500 hours at a cost of $57,750.

However, the production manager now realises that the standard time of 8 hours per unit was the time taken to produce the first unit and that a learning rate of 90% should have been anticipated for the first 600 units.

Required:

(a) Calculate planning and operating variances following the recognition of the learning curve effect.

(b) Explain the importance of learning curves in the context of Target Costing.

Note: The learning index for a 90% learning curve is -0.1520

Solution Preview :

Prepared by a verified Expert
Business Management: A calculate planning and operating variances following the
Reference No:- TGS01557131

Now Priced at $20 (50% Discount)

Recommended (99%)

Rated (4.3/5)