TestDirector in the real time projects

Describe how to use the TestDirector in the real time projects?

E

Expert

Verified

Once completed the preparing of the test cases.

a) Export the test cases into Test Director. (It will comprise total 8 steps).

b) Test cases will be loaded in the Test Plan module.

c) Once the execution is begun, we move to the test cases from Test Plan tab to the Test Lab module.

d) In Test Lab, we execute the test cases and put as fail or pass or incomplete. We make the graphs in the test lab for daily report and sent to the onsite (wherever you want to deliver).

e) If you get any defects and increase the defect in the defect module. Whenever raising the defect, join the defect with screen shot.