What is the slack time associated with non-critical paths


Assignment:

The QuickBuild Construction Company is building a house in the suburb of Oxford, AL. They have the following list of activities, precedence, and (very optimistic, almost fixed) durations for the project.

Activity Predecessors Duration (days)
a. Excavation - 5
b. Pour Foundation A 2
c. Outside Plumbing A 12
d. Framing - 3
e. Wiring B 5
f. Roofing D 1
g. Brickwork B 7
h. Cover Walls C,E 2
i. Exterior Finishing G,F 10
j. Landscapign H,I 6

What is the slack time (in days) associated with any and all non-critical paths through the project?

If activity C were delayed by two time units, what would happen to the entire project duration? Explain. (Show all work with calculation for ES, EF, LS and LF).