Projects expected npv-standard deviation


Scenario Analysis. Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis:

Economic Scenario Probability of Outcome NPV

Recession 0.05 ($70 million)
Below average 0.20 (25 million)
Average 0.50 12 million
Above average 0.20 20 million
Boom 0.05 30 million

What is the project's expected NPV, its standard deviation, and coefficient of variation?