project management earned value calculationa


Project Management Earned Value Calculation

A construction project was 40% complete at month five. The actual cost so far was $100,000; the schedule variance was $20,000 and the spending variance was $-15,000. Evaluate the earned value completed and the total planned cost for the project at completion.