Prepare the contractor and contractees account


Problem:

Model: Contract A/c & Contractee's A/c for 2 years

RBS Ltd took up a construction work of a building at a contract price of 30,00,000. During the first year, the following amounts were spent as against a sum of Rs. 11,25,000 which represented 90% of the work certified and received by the contractor.



Materials

5,25,000

Wages paid to workers

3,00,000

Overhead expenses

75,000

During the second year, the firm spent the following amounts:



Materials

7,50,000

Labour cost

6,00,000

Overhead expenses

1,50,000

In the second year, the contract was completed and a sum of Rs.17,50,000 was received by the contractor. Prepare the contractor and contractee's account for both the years and calculate the profit.

NOTE:Consider only 2/5th of the notional profit that is to be taken to the credit of the profit and loss in the first year, as the work done is less than 50%.