Npv and standard deviations


Problem 1: Two projects have the following NPVs and standard deviations:

 

Project A

Project B

NPV

200

300

Standard deviation

75

100


Which of the two projects is more risky?
 
Problem 2: Your firm has an opportunity to make an investment of $50,000. Its cost of capital is 12 percent. It expects aftertax cash flows (include the tax shields from depreciation) for the next 5 years to be as follows:

Year 1

$10,000

Year 2

20,000

Year 3

30,000

Year 4

20,000

Year 5

5,000


a) Calculate the NPV

b) Calculate the IRR (to the nearest percent)

c) Would you accept this project?

Solution Preview :

Prepared by a verified Expert
Microeconomics: Npv and standard deviations
Reference No:- TGS01748830

Now Priced at $20 (50% Discount)

Recommended (98%)

Rated (4.3/5)