Mrp planning schedule


Problem: In the following MRP planning schedule for item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week.

Item J

0

1

2

3

4

5

Gross requirements

 

 

75

 

50

70

On-hand

 

 

40

 

 

 

Net requirements

 

 

 

 

 

 

Planned order receipt

 

 

 

 

 

 

Planned order release

 

 

 

 

 

 

 

 