Identify the critical path


From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take? Attach or insert your AON network. You may use MSP to check your work, but your submitted file should be similar to that shown in figure 6.8 of Larson & Gray.

ID

Description

Predecessor

Time (days)

A

Survey site

None

2

B

Install drainage

A

5

C

Install power lines

A

3

D

Excavate site

B, C

4

E

Pour foundation

D

3

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Identify the critical path
Reference No:- TGS0676916

Expected delivery within 24 Hours