Find the critical path method-office billing department


Discuss the below:

Q: The home office billing department of a chain of department stores prepares monthly inventory reports for use by the stores purchasing agents. Given the following information use the critical path method to determine:

How long the total process will take.

Which jobs can be delayed without delaying the early start of any subsequent activity.

Jobs and Descriptions                                               Immediate Predecessors            Time(Hours)

A   Start                                                                                        _                                          0

B   Get computer printouts fo customers purchases                   A                                         10

C   Get stock records for the month                                            A                                         20

D   Reconcile purchase printouts and stock records                B,C                                       30

E   Total stock records by department                                      B,C                                       20

F   Determine reorder quantities for coming period                   E                                          40

G   Prepare stock reports for purchasing agents                      D,F                                       20

F   Finish                                                                                   G                                          0

Request for Solution File

Ask an Expert for Answer!!
Project Management: Find the critical path method-office billing department
Reference No:- TGS02030138

Expected delivery within 24 Hours