Eliminate the queue time during production


Bauer Fabrications, Ltd., of Edinburg, Scotland, has recently begun a continuous improvement campaign in conjunction with a move toward Lean Production. Management has developed new performance measures as part of this campaign. The following operating data have been gathered over the last four months:


Month


1 2 3 4
Throughput time ? ? ? ?
Manufacturing cycle efficiency ? ? ? ?
Delivery cycle time ? ? ? ?
Percentage of on-time deliveries 79% 80% 85% 92%
Total sales (units) 10,410 10,590 10,530 10,420

Management would like to know the company's throughput time, manufacturing cycle efficiency, and delivery cycle time. The data to compute these measures have been gathered and appear below:


Month


1 2 3 4
 Move time per unit, in days 0.5
0.7
0.5
0.3
 Process time per unit, in days 0.5
0.8
0.7
0.6
 Wait time per order before start
 of production, in days
9.7
8.0
5.0
4.0
 Queue time per unit, in days 3.0
3.0
2.0
1.0
 Inspection time per unit, in days 0.6
0.7
0.5
0.5

Required:
1a. Compute the throughput time for each month. (Round your answers to 1 decimal place.)

       1        2          3       4
  Throughput time in days


  

1b.

Compute the manufacturing cycle efficiency (MCE) for each month. (Do not round your intermediate calculations and round final answers to one decimal place.)


        1        2       3       4
  Manufacturing cycle efficiency (MCE) % % % %

1c. Compute the delivery cycle time for each month. (Round your answers to 1 decimal place.)

       1          2        3       4
  Delivery cycle time in days


  

3. Refer to the move time, process time, and so forth, given for month 4.
a.

Assume that in month 5 the move time, process time, and so forth, are the same as for month 4, except that through the implementation of Lean Production, the company is able to completely eliminate the queue time during production. Compute the new throughput time and MCE. (Do not round your intermediate calculations and round final answers to one decimal place.)

  Throughput time in days       
  Manufacturing cycle efficiency (MCE) %
b.

Assume that in month 6 the move time, process time, and so forth, are the same as for month 4, except that the company is able to completely eliminate both the queue time during production and the inspection time. Compute the new throughput time and MCE. (Do not round your intermediate calculations and round final answers to one decimal place.)

  Throughput time in days       
  Manufacturing cycle efficiency (MCE)